Minor Irrigation
Drip Irrigation: Part 3
4.0 LAYOUT OF DRIP SYSTEM
The main Line in a drip system should follow land contour as closely as possible. If there is a slope, should be made for pressure differences due to change in elevation. A fall of 1 m in elevation is equivalent to an increase in pressure of about 0.1 atmosphere. Where main lines are laid down on a slope, the increase in pressure due to elevation change may partly compensate the friction head loss. To provide nearly uniform pressure at each emitter, the tubing should be of sufficient diameter to avoid excess friction losses. The water delivered in the supply line is released through emitters spaced along the supply line. The total friction head loss due to lateral openings can be calculated by multiplying the head loss over the total length by a Reduction Co-efficient given in Table 6. However, the additional head loss on account of diversion of flow from the main/laterals into the emitters has to be separately added while estimating the total head for purpose of calculating hp of the pump set. Friction head loss for various flow rates in plastic tubing of different sizes are given in Table 7. The allowable pressure drop in mainline and laterals depend upon the operating pressure required at emitters. The pressure difference between the proximate and distant point along the supply line should not exceed 20% which will keep the variation of discharge within 10% of its value at the first emitter. Table - 6 Reduction Co-efficient 'F' for Multiple Outlet Pipeline Friction Loss Co-efficient | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Table - 7 Friction Head Loss in Meters per 100 m. Pipe Length
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
4.1 Mainline
To design the main line, the pressure required at proximate end of laterals and the maximum friction loss at that point should first be determined. Friction losses due to valves, risers, connectors, etc., should be added to this. Sometimes, two or more laterals simultaneously operate from the mainline and these have to be properly accounted for in the design.
The friction head loss in mains can be estimated by Hazen-Williams formula is given bellow.
hf = 10.68x(Q/C) xD x(L+Le)
Where : hf = Friction head loss in pipe (m)
Q = Discharge (M /sec)
C = Hazen Willian constant (140 for PVC pipe) D = Inner dia of pipe (m) L = Length of Pipe (m) Le = Equivalent length of pipe and accessories 4.2 Laterals
The design of lateral pipe involves selection of required pipe size for a given length to meet the required quantity of water to the plant. This is the most important component of the system as large amount of pipe per unit of land is required and the pipe cost is such that system is economically viable.
In designing the lateral, the discharge and operating pressure at emitters are required to be known and accordingly, the allowable head can be determined by the same formula as the main line.
4.3 Design Criteria
The pressure head of emitter of any lateral should be calculated based on discharge requirement of each emitter.
Friction head loss for various discharges is given in table 8 and equivalent lengths of straight pipe in meters giving equivalent resistance to flow in pipe fittings in Table 9.
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Table-8 : Friction Losses for Flow of Water (m/100m) in smooth Pipes(c=140)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
For other type of pipes (new) multiply foregoing figures by factor given below
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Table - 9 : Length of Straight Pipe in Meter giving Equivalent Resistance to Flow in Pipe Fittings [ IS : 2951 ( Part II ) - 1965 ] (Equivalent Length in Mtrs.)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
5.0 UNIT COST
The unit cost of Drip Irrigation system depends upon the shape and size of command area, spacing and number of plants and their water requirement. The unit cost should include the cost of following main items.
The average unit costs of drip irrigation system for different crops are given in Table-10. This is for guidance only.
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Table - 10 Unit Cost of Drip Irrigation System
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
The Estimated cost of drip irrigation system for Litchi cultivation on 1 ha plot is given in Annexure-I
6.0 Lending terms & Conditions 6.1 Margin Money : The beneficiaries may contribute towards down payment/margin money ranging from 5 to 25% depending upon their category, i.e., small and other farmers in accordance with the NABARD’s norms. Beneficiary’s own labour can also be taken as his contribution towards the margin money requirement. 6.2 Security : As per RBI norms. 6.3 Interest Rate : The rate of interest to be charged to the ultimate borrowers would be decided by the financing banks as per the RBI guidelines from time to time. However, for working out the financial viability and bankability of the model project, the rate of interest is assumed as 12%. 6.4 Repayment Period : Gestation period can be considered while fixing the repayment period. The repayment of interest shall commence from the end of the Gestation period onwards and would continue till the entire principal and interest thereon is repayed. | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Appendix : II
MODEL FOR A SCHEME OF DRIP IRRIGATION This model scheme for drip irrigation system to avail loan assistance give details about estimation of water requirement of plantation crops, system design, HP of pumping unit, unit cost and financial viability of the investment. Let us assume that the beneficiary has an open well of 4m dia and 25 m depth fitted with 5 HP electric pump set. The area has a land slope of 0.5m/100m and the soil is clayey loam. The farmer proposes to install drip irrigation system for a new citrus plantation on a 1ha plot. a. Design parameters Scheme formulation for installation of drip irrigation system against bank loan requires both technical and financial details. The important items that should be included in a scheme for drip irrigation system are given bellow : b. Command area A command area map giving systems layout is necessary to plan and design a drip irrigation system. It may not be necessary to have a detailed contour plan but it is helpful if a plan showing the highest and lowest points along with well location is given in the scheme. This enables proper design of main line and laterals to suit the spacing and number of plants. The present scheme is prepared for application of drip irrigation on one hectare farm of Litchi. c. Spacing and Plant Population of Litchi in one ha. The No of plants required for cultivation of 1 ha litchi with above spacing would be 100m x 100m /6 m x 8 m = 208 plants. However, the plant spacing adopted by earlier farmers was planting at 8x8m to 12x12m. d. Water requirement for litchi plants.
Water requirement for litchi crop (WR) is a function of surface area covered by plants, evaporation rate and infiltration capacity of soil. The irrigation water requirement for each plant has been calculated for each plant and thereafter for the whole plot of 1 ha based on plant population for the different seasons. The maximum discharge required during any one of the three seasons is adopted for design purposes.
The daily water requirement for fully grown plants can be calculated as under.
WR = A X B X C X D X E .................Equation (1)
Where : WR = Water requirement (lpd /plant)
A = Open Pan evaporation (mm/day)
B = Pan factor (0.7) C = Spacing of plant (m2) D = Crop factor (factor depends on plant growth for fully grown plants = 1) E = Wetted Area (0.3 for widely spaced crops ) The total water requirement of the farm plot would be WR x No.of Plants . e. Estimation of Water Requirement
The irrigation water requirement is determined using IMD pan evaporation data. The average season wise pan evaporation data for the area is given below.
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
The daily water requirement of plants using above equation has been worked out as under.
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Therefore, the drip irrigation system has to be designed for the maximum requirement of 65.07 litre /day/plant during the summer season and for this the water required would be 13.53 m3/ day/ha of plantation. If the average working hour of pump set is taken as 4 hours per day, the discharge required would be as below :
Pumping rate per hectare = 13.53 m3 /day/ha = 3.38 m3 /hr/ha = 0.94 LPs or say 1 LPs. As required discharge is only 13.53 m3 /day/ha, it can be pumped for one hour only from a well giving a discharge of 5-6 lps. This is also the normal well yield in the scheme area using a 3-5 HP pump set. For the estimated water requirement of 1 lps only, an arrangement to divert excess water to irrigate other crops would be provided, especially during Kharif and Rabi periods. Alternatively, a tank of 14 m3 capacity can be provided where necessary so that uninterrupted irrigation may continue even in areas where power shut down are frequent. f. Emitters
Depending upon the type of emitter and discharge required their number can be estimated. For a pressure head of 4m and discharge at 17.5 litre /hour the number of emitters required are :
No. of emitters/plant = Rate of Pumping/hour/plant /Avg. discharge of one emitter = 13.53/4 = 3.38 or say 4 emitters/ plant The plot is square and of 1 ha. As such the mainline would be 100 m long and laterals would also be 100 m in length. As plant spacing is 6m x 8m, a total of 13 laterals would be required. Each lateral would serve approximately 16 plants and there would be 4 emitters per plant. Thus, the total number of emitters per lateral would be 16x4 = 64 nos. As the total length of one lateral is 100m the emitters would be spaced at 1.5 m i.e. 100/64. g. Main Line
The main line is designed to carry the maximum discharge required for total number of plants in the farm plot.
Maximum discharge required = No. of plants x peak discharge per plant
= 208x 13.53 = 2814 lph =0.78 or say 1 LPs h. Friction Head loss in Pipes (m)
Total length = 100.0
i. Discharge| Bore diameter(mm)Equivalent length of 13 straight connectors = 6.5 Equivalent length of tee, bends etc = 5.5. Total =112.0 m. The value of coefficients has been taken from tables given below. It would be seen from table 1 that for a discharge of 1 LPs through a pipe of say 40 mm diameter, the friction loss would be 2 m per 100 length or 2.2 m for 112 m equivalent length. Friction Losses for Flow of Water (m/100m) in smooth Pipes(c=140) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
For other type of pipes (new) multiply foregoing figures by factor given below
Friction head loss = 2.2 x 0.88 = 1.94 or say 2.0 Conversion factor = (0.88)
As the proposed system uses multiple openings, the friction loss is taken as 1/3 of the total friction loss i.e. 2.0/3 i.e. 0.66 m. Thus, the loss in mains is within 1.0 m/100 m and a pipe of 40 mm diameter is ideal in the layout.
j. Laterals
A lateral is so selected that the pressure difference from the proximate end to the last emitter do not exceed 10% of the normal operating head which in the present case is 4m. The maximum permissible variation in friction loss in the pipe is 4x10/100 = 0.4 m for a lateral of 100 m length. The land slope is 0.5 m/ 100m. Thus the total friction loss allowable is 0.4 + 0.5 = 0.9 m.
In addition to 100 m length of laterals there is additional loss due to connectors. This is generally taken as 0.1 to 1m (on an average 0.5) of the equivalent length of an emitter. The equivalent length of 64 emitters would thus be 64x0.5 = 32 m. Thus, total equivalent length for calculation of friction loss in laterals would be 132 m (100+32). The total flow in laterals is 256 lph i.e. 4 x 4 x16. It may be seen from Table No 4 that for 200 LPs flow the friction loss in 13.9 m length would be 2.25 m. It is a general practice that friction losses are taken at 1/3 of the total equivalent length of pipes with multiple emitter/connections. Thus, the friction loss works out to 1/3 x 2.25 = 0.75 m which is within the maximum permissible limit of 0.9 m. Therefore, 14 mm (outer dia) lateral pipe of 100 m length is suggested in this scheme.
The friction loss in micro tubes need not be considered as a minimum of 4m head is prescribed which includes friction loss.
Friction Head Loss in M per 100 m. Pipe Length
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
k. HP of Pump set
The HP of pump set required is based upon design discharge and total operating head. The total head is the sum of total static head and friction losses in the system.
(i) Static Head.The total static head is the sum total of the following (m). | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(ii) The friction loss in the drip unit as under (m)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Total Head = Static Head + Friction head loss = 22.25 + 6.95 = 29.20 m or say 30 m
The required HP of the pumpset has been calculated as per the following formula.
Hp of pump set = Q x H/ 75 x e
HP = 1x30 /75x.6 = 0.66 or say 1 HP.Where Q = discharge (lps) H = Head (m) e = Pumping efficiency (o.6) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Appendix - III | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
CHECK LIST
MINOR IRRIGATION - DRIP IRRIGATION
NOTE : Tick (/ ) across the line to signify that the relevant information has been furnished in the scheme.(To be completed by the Executive/Officer of the bank forwarding the scheme) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
No comments:
Post a Comment